Mining
- Hydraulic excavator and 35t trucks
- Strip ratio averages 0.59 over mine life
- Ore feed 7,500 tpd saprolite, 5,000 tpd hard rock
- Optimum feed in saprolite includes 25% hard rock
- Mining in Botija pit first followed by Fortuna
- Total mine workforce is 250
- Feasibility study economics run at $750/oz gold price
|